The Speedway Progress Update: July 2020

The Speedway courtyard construction site viewed through a hole in the interior wall
The courtyard and Building F under construction. Photo by Ella Rinaldo.

Where to begin? When we posted our first Speedway progress update in early March, we never imagined a pandemic would shut down renovations for a month. Nor did we expect that we would have to delay opening until winter, or that the restaurant and retail industries would be thrown into turmoil. While the Speedway construction site came to a standstill, AHF staff worked feverishly to adapt the project to a world of social distancing and economic disruption. Despite these challenges, we’ve managed to move the project forward.

During the shutdown, our main priority was to stay connected with our Brighton neighbors. To this end, AHF connected with State Representative Michael Moran, Charles River Community Health (CRCH), and local wholesaler Katsiroubas Brothers to help address more immediate needs in the community. The result is the Speedway Produce Program. Now in its eighth week, this initiative has delivered 320 boxes of fresh produce, as well as masks, to CRCH members experiencing financial hardship due to the pandemic. AHF sponsored the first month’s worth of produce boxes; thanks to dozens of individual donations and a Harvard University Allston-Brighton Emergency Response Grant, we are able to extend the program until the end of July. Visit our GoFundMe page to help Brighton’s most vulnerable residents access fresh food through the summer.

Meanwhile, the Speedway rehabilitation has progressed by leaps and bounds! Construction restarted in early May after a month-long shutdown. Since then, our contractor D.F. Pray has worked hard to renovate the complex, and it shows:

1. Shingling

If you’ve recently driven past the Speedway, you’ve probably noticed that the Western Avenue and Soldiers Field Road sides of the complex have gotten a makeover. Shingling is nearly complete on the buildings’ public-facing walls, transforming not only the Speedway, but the streetscape itself.

The Speedway's nearly completed shingling along Soldiers Field Road
The Speedway’s shingling is nearly complete along Soldiers Field Road.

2. Repointing Masonry

The masonry of Buildings C and H is being repointed, creating a stable foundation for the buildings’ future tenants – Notch Brewery and a to-be-determined restaurant operator.

Masonry undergoing repointing at the Speedway
The Speedway’s masonry is being repointed.
An open doorway at the Speedway with surrounding masonry being repointed
The masonry around one of the entrances to the Speedway’s Building H is being repointed.

3. A New Roof for the Speedway

The Speedway has a new roof! Ensuring that the complex is water-tight was one of our main priorities when construction got underway again.

The Speedway's Building H with new shingles, new roof, and restored windows
The Speedway’s new roof is now complete.

4. Restoring the Speedway’s Windows

For years, the Speedway’s windows were boarded up – the most visible sign of the blight that had set in at the site. Under the direction of DCR, a Student Conservation Association crew painted fake windows over the plywood, while the 169 real ones were locked away in storage. Now the original windows have been restored and are being re-installed. The difference is unmistakable.

Restored windows at the Speedway
Restored windows are a big improvement for Building H.

5. Ramping and Decking in the Speedway Courtyard

AHF is particularly excited to activate the Speedway courtyard as a public space. Last week, D.F. Pray began laying the foundation for ramping and decking, which will make the courtyard accessible to people of all ages and abilities.

Ramping and decking foundation in the Speedway courtyard
A foundation is being laid for ramping and decking in the Speedway courtyard.

6. Interior Renovations

The interior framing of Buildings E, C, and D –  future creative/retail bays and  Notch’s brewery and taproom – has been restored, allowing for more extensive improvements.  In fact, rough electrical work has begun in Building E!

Interior framing in the Speedway's Building E
The interior framing of the Speedway’s Building E has been restored.
Electrical wires hanging inside one of the Speedway buildings
Rough electrical work has begun inside the Speedway.

Behind the scenes, AHF is preparing to open the Speedway in a radically altered environment. Stay tuned for future announcements as we approach the Speedway’s new opening date in winter 2021.

Architectural Heritage Foundation is a 501(c)3 dedicated to stimulating economic development in disinvested communities through historic preservation. Follow AHF and its projects on FacebookTwitterInstagram, and LinkedIn.

Learn more about the Charles River Speedway revitalization project.

Let’s work together.
info@ahfboston.com